Bridging the Gap

This page shows photographs of the of the progress of the Great Central Railway ‘Bridging the Gap’ project in Loughborough - restoring the rail link between the north of the GCR and the south of the GCR(N), that was removed in the 1980s (see the Old Photographs Section).

 

Click here for a map of this area from Bing
Notes on using the Bing Map
The map linked to is the Ordnance Survey map.
To see an aerial photograph of the area covered by the map click on the tab labelled “Ordnance Survey” near top right of the screen and select ‘Aerial’ from the drop-down list.
When finished with the map click on the browser ‘Back’ button till you return here.

 

This exciting project involves some major civil engineering tasks:

  1. The construction of a bridge over the Midland Main Line at Loughborough.
  2. Reconditioning the original bridge over the canal.
  3. Bridging Railway Terrace.
  4. Rebuilding several hundred metres of embankment.
  5. Relaying track and installing signalling.

The intention is to update this page as work on the project progresses.

 

 

1) Bridge over the Midland Main Line at Loughborough

The first, and the major, civil engineering task of the project was the construction of the bridge over the Midland Main Line, which is now completed save for the final blue facing bricks.

Latest update on the bridge over the Midland Main Line:  March 2018

9/4/17

GCR Bridging the Gap - south embankment removal

9/4/17.  Work has started next to Preci-Spark, on the south side of the Midland Main Line, with the original embankment being reduced in height.  On the right is the Hermitage Brook.

GCR Bridging the Gap - south embankment removal

9/4/17.  Reducing the embankment has revealed the method of construction of the original GCR bridge abutment.  The embankment on the north side can be seen beyond the fence to the right of the signals, 9/4/17.

16/4/17

GCR Bridging the Gap - south embankment removed

16/4/17. On the south side of the Midland Mainline the old embankment has been greatly reduced, but still a couple of feet high has been left and is being covered with chippings.  Most of the old abutment will be retained.
Passing is 66019 with a northbound Network Rail works train.

GCR Bridging the Gap - north embankment piling preparation

16/4/17. A piling auger has arrived and is positioned on the north side of the Midland Mainline ready to bore the holes for the piling.

GCR Bridging the Gap - north embankment piling preparation

16/4/17. Nearby, steel reinforcing assemblies for the concrete piles are being built up.

28/5/17

The original pile boring machine left soon after the last report on 16/4/17, and there was little change from then until a new pile boring machine arrived on 26/5/17.  This larger machine is required because of the higher than expected water table, though this has increased the cost of the project — see http://www.gcrailway.co.uk/unify/.  So work should restart soon.

GCR Bridging the Gap large pile boring machine

28/5/17. The larger pile boring machine stands on the left inside the work compound on the north side of the Midland Mainline.

9/6/17

GCR Bridging the Gap large pile boring machine

9/6/17.  The pile boring machine stands aside while concrete is poured into a bored hole next to the north side of the  Midland Main Line.

GCR Bridging the Gap pouring concrete

9/6/17.  Concrete being poured into a pile hole next to the north side of the Midland Main Line.

23/6/17

GCR Bridging the Gap pile boring machine on south side

23/6/17.  After completing some of the piles on the north side, the pile boring machine was moved overnight to the south side.

6/8/17

GCR Bridging the Gap foundations

6/8/17.  Abutments are being built by forming walls from concrete sections around the piles, inserting reinforcing bars and then filling with ready-mix concrete.  On the south side the new abutment is situated between the old GCR brick abutment and the Midland Main Line.

GCR Bridging the Gap foundations

6/8/17.  The bridge abutments are progressing where the piles were inserted.

10/8/17

GCR Bridging the Gap steel structures on foundations

10/8/17.  Steel structures are being erected on the concrete foundations of the abutments.

27/8/17

Liebherr LG 1750 crane to put the bridge in plces over the gap.

27/8/17.  An enormous Liebherr LG 1750 crane has been used to put the abutment cappings in place and will be used to place the bridge into position.

Liebherr LG 1750 crane and the gap.

27/8/17.  A Meridian on a Nottingham to St. Pancras service passes the gap, which is about ready to take the new bridge, and the Liebherr LG 1750 crane that has been used to put the abutment cappings in place and will be used to place the bridge into position.

3/9/17  The side beams of the new bridge were delivered and installed in the early hours of Sunday 3rd September

Side beam for the new bridge over The Gap

3/9/17, 02:05am.  The steel ropes are attached to the first side beam of the bridge after delivery by lorry.  A Great Central Railway “Bridge to the Future” banner has also been attached.

Lifiting a side beam for the new bridge over The Gap

3/9/17, 02:15am.  The first side beam of the bridge is slowly lifted off the lorry, with perfect weather for the operation; dry and with little breeze.

Lowering into place a side beam for the new bridge over The Gap

3/9/17.  The first side beam of the bridge (the west side) is gently lowered into position on the abutments.

Side beam for the new bridge over The Gap

3/9/17.  The west side beam of the bridge is fixed to the abutments, about 37 years after the original bridge was removed.

New bridge over The Gap in place

3/9/17.  Later that day, an Intercity 125 on the 1F39, 13:55, St Pancras International to Sheffield passes under this new feature over the the Midland Main Line.  The banner that was in place during installation has been removed.

Side beams of the new bridge over The Gap in place

3/9/17.  From the south side of the Midland Main Line the box-section construction of the side beams can be easily seen.  The deck is to be fitted later.
It is readily apparent that the new bridge has been slewed slightly to the east of the original embankment here (the end wall of which can be seen to the left behind the white vehicle), to give room around Preci-Spark.

March 2018:  The bridge over the Midland Mainline is nearing completion

The GCR bridge over the Midland Mainline nearing completion

March 2018.  The bridge is nearing completion with just the final facing blue bricks and the handrails needing fitting on the north side.  Here 66088 passes under the new bridge with a Network Rail ballast train.

The GCR bridge over the Midland Mainline nearing completion

February 2018.  On the south side Preci-Spark have had their car park reinstated.  It is likely that the edge of the car park will be bridged.

For more information about the erection of the bridge over the Midland Main Line visit the Great Central Railway site at http://www.gcrailway.co.uk/unify/bttf.php.

2) Reconditioning the original Canal bridge

The original GCR bridge over the Grand Union Canal in Loughborough was never removed after closure of the line and remains in place approximately 120 years after it was constructed.  Detailed examination of the bridge has shown that it is substantially sound though some reconditioning is required due to corrosion after all this time.  A target of 475,000 has been set to start on the work, and if the money can be raised then it is planned that the work will be carried out when traffic on the canal is very light over the winter of 2018/2019.

For more information visit the Great Central Railway site at http://www.gcrailway.co.uk/unify/.

Latest update on the bridge over the canal:  March 2018

March 2018:  The bridge over the canal is awaiting the raising of the funds to recondition it.

GCR bridge over Grand Union Canal, Loughborough

March 2018.  The GCR bridge over the Grand Union Canal, looking west.

GCR bridge over Grand Union Canal, Loughborough

March 2018.  The GCR bridge over the Grand Union Canal, looking north towards ‘The Gap’.  Laying over the right side of the bridge are corroded tubes which carried fibre optic cables as part of a national network—these have now been disconnected.

GCR bridge over Grand Union Canal, Loughborough

March 2018.  The GCR bridge over the Grand Union Canal, looking south towards the locomotive shed and Loughborough station.  The locomotive shed occupies the original trackbed, and since the shed cannot readily be relocated, it is proposed to route the track to the right of the shed.

Corrosion on the GCR bridge over Grand Union Canal, Loughborough

March 2018.  The bridge is substantially OK, but has some corrosion which will need to be fixed.  The work has been assessed as possible without having to crane the bridge out.

3) Bridging Railway Terrace

To get the railway across Railway Terrace, and possibly the Preci-Spark car park, it is proposed to reuse railway bridges removed by Network Rail during remodelling work at Reading.

GCR 'Bridging the Gap', Railway Terrace bridge abutment

March 2018.  The new bridge over the Midland Main Line is just beyond the old abutment of the GCR at Railway Terrace, which requires a bridge across.  The road on the right leads to the Domestic Refuse Tip.

GCR 'Bridging the Gap', Railway Terrace

March 2018.  Panoramic photograph at Railway Terrace where the abutment in the photograph above can be seen in the centre and the new bridge over the Midland Main Line can be seen on the right.  Bridges will be required to span the road and possibly the Preci-Spark car park.

Bridges from Reading to be used over Railway Terrace for GCR Bridging the Gap

December 2013.  Bridges removed from Reading during a Network Rail upgrade which are proposed to be used to bridge Railway Terrace, and possibly the Preci-Spark car park.  Here they are shown temporarily stored on the 3M site next to the GCR Loughborough station, before being moved to storage elsewhere since this site is being redeveloped.

4) Rebuilding several hundred metres of railway embankment

British Rail removed the railway embankment from north of the canal bridge to Railway Terrace in the 1980s and used the material to build the chord from the GCR(N) to the Midland Main Line before the bridge over the main line was removed (see the Old Photographs Section).

GCR 'Bridging the Gap' missing embankment

March 2018.  The site of the missing embankment looking south from Railway Terrace.  One of the Preci-Spark buildings is on the left and the apex of the roof of the GCR locomotive shed can just be made out to the left of centre.

GCR 'Bridging the Gap' missing embankment

September 2017.  The site of the missing embankment looking north from the bridge over the canal.  The crane in the distance was ready to lift the new bridge over the Midland Main Line into position.

5) Relaying track and installing signalling

When all of the work of rebuilding bridges and the embankment is completed there will still be a large amount of work required in laying track and signalling.

GCR 'Bridging the Gap', train on the GCR(N)

Here, in April 2017, 8F No. 8274 pauses at the furthest south that trains from the GCR(N) at Ruddington can reach on the north side of ‘The Gap’ during scheduled operation.  This is the bridge over Nottingham Road, with the entrance to the Brush works on the left and ‘The Gap’ on the right.  The locomotive has stopped just short of the top of the chord down to the Midland Main Line and the Network Rail track circuit, and will soon propel the train back to Ruddington.

GCR 'Bridging the Gap' from the GCR(N)

Looking south along the track bed of the Great Central Railway at the northern end of ‘The Gap’, just north of its crossing of the Midland Main Line.  Photograph taken from the ‘Ruddington Requiem’ rail tour in June 1984 as it returned from Ruddington and started to traverse the chord from the top of the embankment down to the Midland Main Line .
Track will be required along here together with a new junction with the chord and appropriate signalling linked to the Network Rail system.

GCR 'Bridging the Gap' route of new track past locomotive shed

March 2018.  Near the bridge over the canal, looking south towards the station and the back of Loughborough locomotive shed, with its end wall visible in the centre.  It is proposed that the new track across ‘The Gap’ will be laid to the right of the shed, requiring this area to be tidied up.

GCR 'Bridging the Gap' route of new track past locomotive shed

March 2018.  In this view, looking north from Empress Road bridge, the new track across ‘The Gap’ will be laid to the left of the locomotive shed, seen here on a busy operating day with several locomotives operating out on the line.

GCR 'Bridging the Gap' route of new track past signal box

March 2018.  The new track across ‘The Gap’ would have to run straight ahead in front of the signal box and under the left side of Empress Road bridge in order to pass alongside the locomotive shed.
The signalling system of the GCR will have to be linked to GCR(N), across the gap, which is already connected to the Network Rail system to allow Gypsum trains from the Midland Main Line to reach the Hotchley Hill Gypsum works via the 1980s chord.

For more information about ‘Bridging the Gap’ visit the Great Central Railway site at http://www.gcrailway.co.uk/unify/.

© 2001-2018   Text and photographs copyright Nigel Tout, unless otherwise indicated.